Project Summary

Retroflo were engaged by Esh/Stantec (supported by NWG) to undertake the mechanical and electrical installation of the new tertiary solids removal treatment plant at Stokesley STW. The project included pipework, valves, electrical sub-distribution, and system integration for telemetry and SCADA. Works also included installation of a new sump pump, modifications to existing street lighting, and completion of NICEIC 18th Edition inspection, testing, commissioning, and associated documentation. The upgrade improves the performance and compliance of Stokesley STW.

Scope of Works

Retroflo provided a full end-to-end service, including:

  • Supply and installation of above-ground 350 mm and 300 mm ductile iron pipework and valves
  • Supply and installation of above- and below-ground 80 mm ductile iron backwash pipework and valves
  • Electrical design including cable calculations, SLDs, cable diagrams and loop diagrams
  • Supply and installation of electrical sub-distribution for new process plant with provision for future equipment
  • Engagement of system integration subcontractor for telemetry and SCADA works
  • Installation of a new sump pump
  • Modifications to existing street lighting installation
  • Mechanical and electrical installation, commissioning and associated documentation
  • NICEIC 18th Edition inspection, testing and certification
  • Power distribution and control panel installation

Results

  • Fully compliant tertiary solids removal solution
  • Reliable hydraulic and electrical performance
  • Future-ready power distribution and telemetry integration
  • Turnkey delivery completed on time with full certification
Project Details
Client

Esh/Stantec (supported by NWG)

Project Value

£1,000,000

Project Highlights
Enhanced Tertiary Treatment Performance

Retroflo delivered the mechanical and electrical installation of the new tertiary solids removal plant at Stokesley STW, improving treatment performance and compliance.

Comprehensive Pipework & Valve Installation

Above- and below-ground ductile iron pipework and valves were installed, including 350 mm, 300 mm, and 80 mm backwash systems, ensuring reliable hydraulic operation.

Advanced Electrical & Control Systems

New electrical sub-distribution, power distribution, and control panels were installed, designed with capacity for future plant expansion. NICEIC 18th Edition inspection, testing, and certification were completed as part of full commissioning.

Integrated Telemetry & SCADA

System integration for telemetry and SCADA was coordinated, providing real-time monitoring, control, and improved operational reliability. Additional works included a new sump pump and modifications to existing street lighting, all delivered under a turnkey M&E scope.