Retroflo Services
Case Studies

UK Tapes Electrical Installation

CLIENT: Uk Industrial Tapes

DATE: December 2017

PROJECT: Supply intake alterations, new sub main cables and distribution boards, wiring to new extension, extension to fire alarm and emergency lighting.

SCOPE OF WORK: Initial liasing with the supply and meter op­erators to facilitate an upgrade to the supply within the site. Project management of the civils trench works and Northern Powergrid operatives to upgrade the incoming supply. Installation of 315A main switch and supply cable to the existing switch board .Installation of sub main cable and 16 way TPN DB to the rear of the warehouse in read­iness for future works. Upgrading of the earthing system. Installation of sub main cable and 11 way SP DB to the new extension. Electrical installation within new extension.

Open the Case Study

CLIENT: Northumbrian Water Group

DATE: December 2015 – Jan 2016

PROJECT: Flood Alleviation Site Situated in Houghton-Le-Spring

SCOPE OF WORK: Works consisted of installing a Flood Alleviation pumping station in Houghton-Le-Spring. Retroflo were contracted to supply, install and commission the Mechanical and Electrical works of the site. This included the supply of the Motor Control Center (MCC), Instrumentation, interconnecting cable and associated junction boxes, containment items and earthing installation. Kiosks to house the MCC and REC equipment were also installed.

Open the Case Study

CLIENT: Jotron Ltd

DATE: October 2017

PROJECT: Installation of 2no Commercial EV charging pedestal via time clock and contactor.

SCOPE OF WORK:

Project included civil works including trench and internal wall break out for cables, back filling trench works, form shutter and form concrete plinth works. Electrical work included installing SWA cabling to trenches, installing distribution board, time clock, contactor and 2x 16A pedestal units to plinth.

Open the Case Study

CLIENT: Persimmon Homes

DATE: September 2014 – March 2015

PROJECT: Persimmon Homes housing development at Ingleby Barwick

SCOPE OF WORK: Retroflo’s experienced engineering team were employed to carry out the detailed M&E and civil design of the foul pumping station required at the new development in Ingleby Barwick.

Open the Case Study